Changeover time for piling plant reduced by optimising use of a 2nd excavator
Lean Project Benefits Summary
*
Programme time of 29hrs mitigated and associated savings of £37,825.59
Roads Period Efficiency Reported
RP1 2015-2020
RP2 2020-2025
RP3 2025-2030
N/A
Efficiency Value Assured
*
Efficiency Register ID
Image
Choose File
---
Lean Construction Development Programme (LCDP) Project
Lean Construction Development Programme (LCDP) Project
No
Lean Construction Development Programme (LCDP) Project
Yes
Supplier
*
Contact Email
*
*
*
Stakeholders involved in project
*
Stakeholders Involved - Other
*
Problem Solving Strategy (DMAICT)
Define
*
A retrofit programme has been developed to create additional Emergency Areas (EAs) on sections of ALR motorway across the country giving drivers added reassurance and confidence in the safety of the Network. 150 additional EAs are being added to ALR motorways by the SMP Alliance. There is opportunity to understand the construction process, variants and lessons learnt from previously built EAs. The sheetpiling activity is one that will be repeated on a number of EA's and suitable for a Lean study
Measure
*
For the first week of activity on Emergency Area EA02 on DHS M6 J4-5 we carried out a series of direct work observations during the Sheet piling works. We worked with the piling contractor Van Elle to look for opportunities for improvement. Daily records were maintained of production and of resource that was used.
Analyse
*
We analysed the sheet piling records from week 1. It was observed that the second excavator was not being utilised. We identified a risk that time would be lost through transport and motion by changing equipment from the pre auger to the vibrating hammer. We forecast it was going to take 14.9 days to complete the activity based on the current progress. An intervention was required to mitigate the programme.
Improve
*
Our Engineer discussed the proposed method of works for pre auguring and sheet piling using a single excavator with Van Elle and suggested an alternative method to make use of the second excavator and thus reduce change over time. Support was gained from the Senior Agent
Control
*
The pre auguring, vibrating and pile hammering activity was monitored and recorded through week 2 to verify the improved production that could be achieved using 2 excavators thereby reducing the changeover time of piling attachments on the excavators.
Transfer
*
The A3 report was generated. A PowerPoint Presentation was prepared for sharing to a wider forum. National Highways Efficiency Register ID 1587
What Lean Tools & Methodologies were used for your Lean Project?
If Other, please specify
*
Other Project Benefits
Meeting the needs of all users
Meeting the needs of all users - Other
*
Improving safety, health & wellbeing for all
Improving safety, health & wellbeing for all-Other
*
Delivering better environmental outcomes
Delivering better environmental outcomes - Other
*
Sustain a well-maintained and resilient network
Sustain well-maintained & resilient network- Other
*
Providing fast and reliable journeys
Providing fast and reliable journeys - Other
*
Achieve efficient delivery
Achieve efficient delivery - Other
*
Project Detail
National Highways Directorates involved in project
*
Division
Scheme Name
*
Scheme PIN
*
Was a Departure Required?
Was a Departure Required?
No
Was a Departure Required?
Yes
DAS Reference
*
How would you categorise your Lean project?
Uploaded Files
There are no notes to display.
You don't have permissions to view notes.
Error completing request.
Loading...
Loading...