Project Summary
Lean Project Name
*
*
Unique ID
*
Lean Project Description
*
*
Lean Project Summary
*
Reduced the number of the steps in the process from 32 steps to 8
Lean Project Benefits Summary
*
Reduced rework and clarity on the process, saving an overall duration of 30 days and £2005.69 per communication.
Roads Period Efficiency Reported
RP1 2015-2020
RP2 2020-2025
RP3 2025-2030
N/A
Efficiency Value Assured
*
£
Efficiency Register ID
Image
Choose File
---
Lean Construction Development Programme (LCDP) Project
Lean Construction Development Programme (LCDP) Project
No
Lean Construction Development Programme (LCDP) Project
Yes
Supplier
*
Contact Email
*
*
*
Stakeholders involved in project
*
Stakeholders Involved - Other
*
Problem Solving Strategy (DMAICT)
Define
*
The process for External communications was not defined, or consistent. This led to delays, confusion, and in turn some relationship breakdowns.
Measure
*
We carried out a Current State Value Stream Map where we identified the waste and overall duration of the process. We looked at this as a percentage, identifying which parts of the Value stream map were wastes such as rework and overprocessing, which helped to identify areas for improvement.
Analyse
*
We measured the current state at 20,140 Minutes or 41. 9 days including Weekends. The percentage of Waste was 98.41%, with 0.65% NVA, and 0.94% Value Adding. the main Wastes identified included Overprocessing and Rework.
Improve
*
We completed a future state for the process and also identified further improvements that could be made at a later date. We reduced the number of the steps in the process from 32 steps to 8, the benefits included reduced rework, clarity on the process to follow, saving an overall duration of 30 days, improving our relationship with external stakeholders and the customer, and saving £2005.69 per communication. Reducing waste by 4% and overall time by 71.43%.
Control
*
The future state process has been distributed across the RDP Midlands. The process is being tested by all schemes as fit for purpose. Once tested, this will go out as best practice across all RDP schemes.
Transfer
*
Once tested and finalised this will go out as best practice across all RDP schemes. As part of Lean Construction Development Programme (LCDP) efficiencies under National Highways Efficiency Register ID 1075
What Lean Tools & Methodologies were used for your Lean Project?
If Other, please specify
*
Other Project Benefits
Meeting the needs of all users
Meeting the needs of all users - Other
*
Improving safety, health & wellbeing for all
Improving safety, health & wellbeing for all-Other
*
Delivering better environmental outcomes
Delivering better environmental outcomes - Other
*
Sustain a well-maintained and resilient network
Sustain well-maintained & resilient network- Other
*
Providing fast and reliable journeys
Providing fast and reliable journeys - Other
*
Achieve efficient delivery
Achieve efficient delivery - Other
*
Project Detail
National Highways Directorates involved in project
*
Division
Scheme Name
*
Scheme PIN
*
Was a Departure Required?
Was a Departure Required?
No
Was a Departure Required?
Yes
DAS Reference
*
How would you categorise your Lean project?
Uploaded Files
There are no notes to display.
You don't have permissions to view notes.
Error completing request.
Loading...
Loading...