Project Summary
Lean Project Name
*
*
Unique ID
*
Lean Project Description
*
*
Lean Project Summary
*
To understand the reasons for KPI failures against roadwork accuracy in Yorkshire North-East
Lean Project Benefits Summary
*
Accurate customer information Programme stability Fewer short notice changes Improved performance against Office of Road & Rail (ORR) target (National Highways 90% accuracy target for notifying road users about overnight road closures seven days in advance).
Roads Period Efficiency Reported
RP1 2015-2020
RP2 2020-2025
RP3 2025-2030
N/A
Efficiency Value Assured
*
Efficiency Register ID
Image
Choose File
---
Lean Construction Development Programme (LCDP) Project
Lean Construction Development Programme (LCDP) Project
No
Lean Construction Development Programme (LCDP) Project
Yes
Supplier
*
Contact Email
*
*
*
Stakeholders involved in project
*
Stakeholders Involved - Other
*
Problem Solving Strategy (DMAICT)
Define
*
National Highways has a 90% accuracy target for notifying road users about overnight road closures seven days in advance. We cancel a significant number of our planned full and slip road closures inside the 7 day locked down period, often for reasons that are within the team's control. This project aimed to understand the reasons why this occurred and agree on the required improvement actions to reduce average number of bookings not being utilised.
Measure
*
Data was collected and using Power BI showed that the top 5 reasons for failure were: * Weather *Reprogramming *Safety *Booking error *Works completed early.
Analyse
*
Pareto analysis, 5 whys and Fishbone Analysis were used to identify the root cause and understand the reasons in more detail. To ensure the team were focusing on issues they had control and influence over, we undertook a sphere of influence activity, rather than focusing the team's time discussing issues that couldn't be improved, such as weather.
Improve
*
Identified 3 areas of improvement: 1) A more robust make ready process, 2) Improve communications between the Regional Operations Centre (ROC) and contractor, 3) Improved capability on the relevant systems to address the booking error fault to improve quality and accuracy of bookings.
Control
*
To monitor performance, weekly standard meetings are set up where issues are reported and captured and assigned owners. Performance is continually reviewed through Power BI, which has captured the impact from the improvements made.
Transfer
*
Review key processes. Verification process between road space occupancy teams and contractors that planned roadworks accurate. Look at opportunities to standardise and refresh training on the current systems, so there is consistency in how the systems are used to improve the accuracy on informative and data captured. Understand where communications/interactions occur (in this case between the ROC and the contractor) and the impact those interactions have on performance, identifying opportunities for effective productive communications with increased understanding of the ROC requirements. Verify how data is recorded, manual capture/digital as it was identified through the Lean workshop that all delays were being manually recorded as an hour, this meant those roadworks failed the Key Performance Indicators (KPI), with delays that had passed the KPI as under an hour being counted in the number of roadworks that failed the 7 day accuracy KPI, negatively impacting performance reports.
What Lean Tools & Methodologies were used for your Lean Project?
If Other, please specify
*
Other Project Benefits
Meeting the needs of all users
Meeting the needs of all users - Other
*
Improving safety, health & wellbeing for all
Improving safety, health & wellbeing for all-Other
*
Delivering better environmental outcomes
Delivering better environmental outcomes - Other
*
Sustain a well-maintained and resilient network
Sustain well-maintained & resilient network- Other
*
Providing fast and reliable journeys
Providing fast and reliable journeys - Other
*
Achieve efficient delivery
Achieve efficient delivery - Other
*
Project Detail
National Highways Directorates involved in project
*
Division
Scheme Name
*
Scheme PIN
*
Was a Departure Required?
Was a Departure Required?
No
Was a Departure Required?
Yes
DAS Reference
*
How would you categorise your Lean project?
Uploaded Files
There are no notes to display.
You don't have permissions to view notes.
Error completing request.
Loading...
Loading...