Lean Tracker Knowledge Database

Kier A585 Delivery ticket reconciliation improvement project

Kier A585 team reduced invoices on hold by 50% by streamlining delivery ticket processes and improving supplier payments

Kier A585 Scheme: Environmental Reporting Quality Improvement Project

Kier’s A585 team enhanced compliance on the A585 scheme by increasing environmental observations and preventing incident

Kier A417 Missing Link Bailey Bridge Design Improvement Project

Kier's A417 team resolved Bailey bridges design issue to shorten delivery timeline, reduced risk and cost significantly.

Kier A417 Missing Link: Permit Receiver Booklet Improvement Project

Kier A417 Permit Receiver Booklet standardises permit checks and improved compliance across Project

Kier A585 Windy Harbour: Optimisation of Skippool Bridge sleeve diameter design

Kier’s A585 team optimised the sleeve diameter design by 150mm at Skippool Bridge, enhancing network resilience.

Kier A585 Lodge Lane Retaining Wall Improvement Project

Kier's A585 team reduces Lodge Lane Wall from 400m to 300m by adapting embankments reducing costs and material usage.

SDF lean project delivery via the YNE Collaborative Community (YNECC)

A1 Oak Grange Drainage Improvement Scheme optimized the benefits of lean delivery using ECI and collaborative working

Improving SDF site visit safety using lean & digitalisation

Improving SDF site visit safety using lean & digitalisation of "Point of Work Risk Assessments" (PowRA)

Kier A417 Missing Link: Solar-Hybrid -powered lighting sustainable Solution

Kier A417 Missing Link: Solar hybrid power reduce fuel use by 75%, saving £394,466 and reducing CO₂e by 495,273 kg/year.

Regulatory Monitoring & ORR Relations SharePoint

The Regulatory Monitoring Team have split into two distinct teams but still using the same internal SharePoint page.

Converting HVO to LPG Generators

Converting HVO to LPG Generators

Kier A585 Lodge Lane Piling Improvement Project

Kier team ensures piles are cropped after concrete reaches specified strength, meeting tight tolerances for orientation

Kier IBIP Observation reporting process Improvement Project

Kier’s A417 team standardised IBIP reporting and improved data analysis, enhancing team performance and project outcomes

Kier A585 Scheme Drainage Run Reviews Improvement Project

Kier's A585 team engaged utility companies in Preliminary Design to avoid diversions, reduce costs, and adapt designs.

50% faster Bored Piling based on Direct Works Observations

Use of Direct Works Observations to inform process improvement for bored piling on M1 Emergency Area Program

Introducing "Tasks Made Ready" - to optimise Collaborative Planning

Introducing Tasks Made Ready reviews to Collaborative Planning routine, one of 7 layers of protection to programme

Improvements to Installation of Redi-Rock Retaining Wall

Improvements to Installation of Redi-Rock Retaining Wall

Improved plunge pile installation outputs

Improvements to plunge pile installation productivity

M40-M42 Interchange - Use of Collaborative Planning

Use of collaborative planning system to manage short term programme

Collab Planning & Production Management Implementation on NH TA2 Framework

Implementation of Lean production management processes on TA2 schemes to drive higher levels of delivery reliability

LCDP - Use of permanent formwork for concrete foundation slabs

Improve construction output of concrete foundation slabs

Central Reserve Concrete barrier installation

The M40/M42 Interchange scheme had 11km of central reserve concrete barrier to construct in 8 months

Productivity Improvement - Construction of Emergency Refuge Areas - Sheetpiling

Improvements to sheetpiling activity

Improved management of keys

Keys did not have a specific safe storage location with a consistent, robust management process in place for them

Project Name Project Description Core Processes Supplier
Kier A585 Delivery ticket reconciliation improvement project Kier A585 team reduced invoices on hold by 50% by streamlining delivery ticket processes and improving supplier payments Service Delivery Kier
Kier A585 Scheme: Environmental Reporting Quality Improvement Project Kier’s A585 team enhanced compliance on the A585 scheme by increasing environmental observations and preventing incident Scheme Delivery Kier
Kier A417 Missing Link Bailey Bridge Design Improvement Project Kier's A417 team resolved Bailey bridges design issue to shorten delivery timeline, reduced risk and cost significantly. Scheme Delivery Kier
Kier A417 Missing Link: Permit Receiver Booklet Improvement Project Kier A417 Permit Receiver Booklet standardises permit checks and improved compliance across Project Health Safety & Wellbeing Kier
Kier A585 Windy Harbour: Optimisation of Skippool Bridge sleeve diameter design Kier’s A585 team optimised the sleeve diameter design by 150mm at Skippool Bridge, enhancing network resilience. Construction Kier
Kier A585 Lodge Lane Retaining Wall Improvement Project Kier's A585 team reduces Lodge Lane Wall from 400m to 300m by adapting embankments reducing costs and material usage. Construction Kier
SDF lean project delivery via the YNE Collaborative Community (YNECC) A1 Oak Grange Drainage Improvement Scheme optimized the benefits of lean delivery using ECI and collaborative working Scheme Delivery Jacobs
Improving SDF site visit safety using lean & digitalisation Improving SDF site visit safety using lean & digitalisation of "Point of Work Risk Assessments" (PowRA) Scheme Delivery Jacobs
Kier A417 Missing Link: Solar-Hybrid -powered lighting sustainable Solution Kier A417 Missing Link: Solar hybrid power reduce fuel use by 75%, saving £394,466 and reducing CO₂e by 495,273 kg/year. Environmental Management Kier
Regulatory Monitoring & ORR Relations SharePoint The Regulatory Monitoring Team have split into two distinct teams but still using the same internal SharePoint page. N/A National Highways
Converting HVO to LPG Generators Converting HVO to LPG Generators Construction Costain
Kier A585 Lodge Lane Piling Improvement Project Kier team ensures piles are cropped after concrete reaches specified strength, meeting tight tolerances for orientation Construction Kier
Kier IBIP Observation reporting process Improvement Project Kier’s A417 team standardised IBIP reporting and improved data analysis, enhancing team performance and project outcomes Construction Kier
Kier A585 Scheme Drainage Run Reviews Improvement Project Kier's A585 team engaged utility companies in Preliminary Design to avoid diversions, reduce costs, and adapt designs. Construction Kier
50% faster Bored Piling based on Direct Works Observations Use of Direct Works Observations to inform process improvement for bored piling on M1 Emergency Area Program Scheme Delivery Jacobs
Introducing "Tasks Made Ready" - to optimise Collaborative Planning Introducing Tasks Made Ready reviews to Collaborative Planning routine, one of 7 layers of protection to programme Scheme Delivery Jacobs
Improvements to Installation of Redi-Rock Retaining Wall Improvements to Installation of Redi-Rock Retaining Wall Construction BAM Nuttall
Improved plunge pile installation outputs Improvements to plunge pile installation productivity Construction BAM Nuttall
M40-M42 Interchange - Use of Collaborative Planning Use of collaborative planning system to manage short term programme Construction BAM Nuttall
Collab Planning & Production Management Implementation on NH TA2 Framework Implementation of Lean production management processes on TA2 schemes to drive higher levels of delivery reliability Jacobs
LCDP - Use of permanent formwork for concrete foundation slabs Improve construction output of concrete foundation slabs Construction BAM Nuttall
Central Reserve Concrete barrier installation The M40/M42 Interchange scheme had 11km of central reserve concrete barrier to construct in 8 months Construction BAM Nuttall
Productivity Improvement - Construction of Emergency Refuge Areas - Sheetpiling Improvements to sheetpiling activity Construction BAM Nuttall
Improved management of keys Keys did not have a specific safe storage location with a consistent, robust management process in place for them Construction BAM Nuttall

Latest Lean Content

icon-point

Get in Touch

If you cannot find what you are looking for the National Highways Lean team are available to help.

Lean Tracker Admin: leantracker@nationalhighways.co.uk

National Highways Lean team: leanimprovement@nationalhighways.co.uk